Godawari Q2 profit drops to Rs85 crore on high-cost ore and coal as board clears over Rs1,400 crore new capex and Rs2,795 crore guaranteed debt
Godawari Power and Ispat digs its own iron ore and turns it into pellets, sponge iron and steel bars and wires for buildings, bridges and power lines, saving cost with captive mines and power. On 13 November 2026 its board approved unaudited results for the quarter and half year ended 30 September 2026 plus battery, steel value-add, fleet and solar moves and a new brand logo . The takeaway is that steel earnings slipped sharply from the June quarter on costly market ore and fuel while sales stayed above last year, as growth and leverage shift toward batteries and higher-value steel.
Q2 and H1 FY27 in one view
The filing covers standalone books and consolidated group results for the quarter and half year ended 30 September 2026 . The company said it has only one reportable operating segment for manufacture of steel products .
Source: .
| Measure | Consolidated Q2 FY27 | Standalone Q2 FY27 |
|---|---|---|
| Revenue from operations (Rs crore) | 1631.53 | 1410.53 |
| Total income (Rs crore) | 1654.81 | 1434.26 |
| Profit before tax (Rs crore) | 120.41 | 134.12 |
| Net profit (Rs crore) | 85.00 | 102.19 |
| Basic EPS (Rs) | 1.38 | 1.57 |
| Diluted EPS (Rs) | 1.32 | 1.52 |
| Exceptional item (Rs crore) | -22.33 | 1.24 |
The quarter was softer than the June quarter but revenue stayed above the same quarter last year on both books . Profit was lower sequentially as costs stayed high and a one-off hit weighed on the consolidated book .
Sources: Q2 FY27 — ; earlier quarters — .
| Period | Revenue from operations (Rs crore) | Net profit (Rs crore) |
|---|---|---|
| Q2 FY26 | 1307.68 | 161.65 |
| Q3 FY26 | 1139.45 | 143.45 |
| Q4 FY26 | 1610.27 | 280.23 |
| Q1 FY27 | 1750.47 | 222.37 |
| Q2 FY27 | 1631.53 | 85.00 |
Half-year revenue was higher than last year while profit was lower .
Source: .
| Measure (Rs crore) | Consolidated H1 FY27 | Consolidated H1 FY26 | Standalone H1 FY27 | Standalone H1 FY26 |
|---|---|---|---|---|
| Revenue from operations | 3382.00 | 2630.93 | 2897.19 | 2276.50 |
| Net profit | 307.37 | 378.05 | 301.09 | 448.90 |
Annual history shows flat sales with stable profit, framing this quarter as a margin dip rather than demand collapse .
Source: .
| Period (Rs crore) | Consolidated revenue | Consolidated net profit | Standalone revenue | Standalone net profit |
|---|---|---|---|---|
| FY24 | 5455.35 | 935.59 | 5042.12 | 917.44 |
| FY25 | 5375.73 | 812.98 | 4661.24 | 769.64 |
| FY26 | 5380.65 | 801.74 | 4713.96 | 919.43 |
The May 2026 presentation called FY26 resilient despite softer realizations, with consolidated EBITDA margin of 23 percent and PAT margin of 15 percent . It noted Q4 FY26 revenue up 41 percent quarter on quarter on higher volumes and better realizations .
Why profit fell: market ore, coal and gas
Costs stayed high against last year while finance cost and depreciation rose .
Sources: Q2 FY27 — ; earlier quarters — .
| Period, Consolidated (Rs crore) | Cost of materials | Other expenses | Finance cost | Depreciation |
|---|---|---|---|---|
| Q2 FY26 | 706.58 | 246.78 | 11.24 | 41.31 |
| Q1 FY27 | 973.56 | 333.00 | 20.33 | 50.05 |
| Q2 FY27 | 946.92 | 329.75 | 24.78 | 52.24 |
Management had called Q1 FY27 a steady start on healthy sales and better realization, with EBITDA margin at 19.1 percent and PAT margin at 12.7 percent . It tied sequential pressure to market ore and elevated coal after the West Asia crisis .
Source: .
| Input pressure flagged on 10 August 2026 call | Detail |
|---|---|
| Cost increase split | iron ore about 75 percent, imported coal about 25 percent |
| Imported coal price | about Rs10,500 in Q4 and early Q1, touched almost Rs13,000 |
| Gas purchase value | up 40 to 45 percent under new guidelines |
| Pellet low | touched about Rs8,700 in early July, below Rs9,000 in late June and early July |
| Pellet sensitivity | Rs100 fall loses about Rs40 crore a year on 40 lakh tonnes |
The new 20 lakh tonne pellet plant became unviable at those lows, forcing a shutdown through August with a possible restart in September .
Source: .
| Pellet operations | Detail |
|---|---|
| Q1 use | all three plants ran, extra output sold as merchant as captive use stayed flat |
| Shutdown | one 20 lakh tonne plant shut almost 45 days to August |
| Q2 view | about 500 kt if shut all quarter |
| FY27 pellet view | 40.00 lakh tonnes, slightly lower |
Mining fell on overburden dumping space pending tree-cutting permission, forcing market buys . The path back is mine beneficiation and EVs to cut mining cost .
Source: .
| Mining and captive path | Detail |
|---|---|
| Q1 mining cost | between Rs3,000 to Rs3,500 |
| Target from FY28 | below Rs2,700 via mine beneficiation and EVs |
| Saving rule | Rs100 saving gives Rs45 crore to Rs50 crore EBITDA on 50 to 60 lakh tonnes ore |
| Captive path | 25 to 30 percent market buy in Q3, below 10 percent from Q4, 100 percent captive in FY28 |
The May call gave the longer price context around Q4 FY26, when revenue jumped on stock sale, new pellet output and extra March mining .
Source: .
| Q4 FY26 rebound driver | Detail |
|---|---|
| Pellet stock sold | about 89,000 tonnes carried from Q3 |
| Inventory gain | about Rs20 crore |
| New pellet plant | started end December, reached about 70 percent capacity |
| Extra March mining | 2 to 2.5 lakh tonnes after clearance |
Q4 pellet realization lagged the market as limited captive ore forced lower-grade commercial pellets over high-grade pellets that earn over Rs1,000 premium . Mix was seen improving from Q3 FY27 after monsoon .
Source: .
| Pellet capacity and FY27 view | Detail |
|---|---|
| Capacity | from 27.00 lakh tonnes to 47.00 lakh tonnes in December 2025 |
| FY27 split | merchant about 30 lakh tonnes, captive 9 to 10 lakh tonnes |
| FY27 sales and margin view | top line to cross Rs6,000 crore, EBITDA 24 to 25 percent at current levels |
| Conversion | mining to pellet about Rs2,000, iron ore about 40 percent, coal about 35 percent |
Balance sheet and cash: capex already running hot
Assets grew on plant and work in progress while other bank balances fell and borrowings rose from March to September 2026 .
Source: .
| Consolidated item (Rs crore) | 30 Sep 2026 | 31 Mar 2026 |
|---|---|---|
| Property, plant and equipment | 3460.68 | 3284.31 |
| Capital work in progress | 693.72 | 469.51 |
| Inventories | 1078.35 | 926.36 |
| Trade receivables | 117.35 | 131.54 |
| Cash and cash equivalents | 352.28 | 306.16 |
| Other bank balances | 351.45 | 838.43 |
| Assets held for sale | 222.66 | 0.00 |
| Non-current borrowings | 328.60 | 238.08 |
| Current borrowings | 391.78 | 188.61 |
| Total equity | 6125.08 | 5849.01 |
Operating cash covered only part of the build, with the balance met by financing in the half year .
Source: .
| Cash line H1 FY27 (Rs crore) | Consolidated | Standalone |
|---|---|---|
| Operating cash | 260.68 | 311.73 |
| Investing use | -433.48 | -470.74 |
| Buy of plant, equipment and work in progress | -944.45 | -608.88 |
| Financing inflow | 218.92 | 179.76 |
For context, FY26 operating cash improved 29 percent to Rs1,157 crore with a net cash position of Rs837 crore described in May . The matrix shows FY26 borrowings of Rs426.69 crore against Rs308.59 crore in FY25 with debt to equity of 0.07 times .
Batteries take centre stage: 3 GWh for factories plus Rs2,795 crore debt
The board cleared a new commercial and industrial storage line in the battery arm and a large debt and guarantee package .
Source: .
| Approval on 13 Nov 2026 | Detail |
|---|---|
| 3 GWh project cost | Rs135 crore at Auric, Sambhajinagar, commissioning by March 2028 |
| Funding | additional Rs135 crore from GPIL in GNEPL |
| Extra storage line | Rs110 crore for new commercial and industrial energy storage |
| Total in GNEPL | Rs810 crore, up from Rs700 crore |
| GNEPL debt | Rs2,795 crore with corporate guarantee |
| Debt split | term Rs700 crore, working capital Rs2,095 crore with fund Rs100 crore and non-fund Rs1,995 crore |
This sits alongside a larger 20 GWh base already under build .
Source: .
| 20 GWh base | Detail |
|---|---|
| Cost and funding | Rs1,400 crore, 1 to 1 debt to equity |
| Spent to 31 Mar 2026 | Rs310 crore |
| Land | 112 acres at Auric, soil test done, wall work on |
| Partners | cells EVE Power, balance of system Roche Energy, conversion Fimer India and Hopewind |
| Commissioning then guided | March 2027 |
By August, spend had risen with machine delivery and first container timelines set .
Source: .
| Update in August 2026 call | Detail |
|---|---|
| Spent to date | Rs501 crore |
| Machine delivery | from December 2026 |
| First container | Q1 FY28 |
| Commissioning | Q1 FY28 |
| Remaining capex for rest of FY27 and FY28 | Rs700 crore to Rs800 crore |
Funding into the arm has come in steps since its creation in June 2025 .
Sources: creation — ; May approval — ; June step — ; July step — ; Sept preference — ; clearance — .
| Step | Detail |
|---|---|
| Vehicle | Godawari New Energy set up 25 June 2025 as wholly owned unit for first-phase battery plant |
| May 2026 approval | total help to Rs700 crore |
| June 2026 equity | Rs100 crore to reach Rs450 crore |
| July 2026 equity | Rs150 crore to reach Rs600 crore |
| Sept 2026 preference | Rs50 crore |
| Oct 2026 clearance | environment clearance for Auric Bidkin building |
Management guided remaining capex of close to about Rs2,000 crore for the rest of FY27 and FY28, to be met from free cash flows with the steel plant on hold .
Steel value-add moves to Maharashtra: cold rolling mill and containers
The board moved the sheet-steel mill to Maharashtra and added a container line beside it .
Source: .
| Move approved 13 Nov 2026 | Detail |
|---|---|
| Mill shift | from Sarora, Tilda to Auric, Bidkin, Sambhaji Nagar |
| Revised cost | Rs1,100 crore including land and working capital margin |
| Container line | Rs100 crore alongside mill, commissioning by March 2028 |
| Container capacity | 10,000 numbers of 20 ft containers and 12,000 small cabinets per annum |
The earlier plan was a Chhattisgarh mill for cold rolled products .
Source: .
| Earlier 7.00 lakh tonne mill plan | Detail |
|---|---|
| Cost | Rs900 crore with Rs550 crore debt sanctioned |
| Land | acquisition completed |
| Build start | expected from July 2026 |
| Spent to 31 Mar 2026 | Rs73 crore |
| Commissioning | March 2027 |
| Incentive | registered under PLI 1.1 and 1.2 |
In August, management linked the move to state incentives and auto-hub demand near Sambhaji Nagar .
Source: .
| Relocation update August 2026 | Detail |
|---|---|
| Site | about 35 acres at about Rs50 crore near Sambhaji Nagar |
| Allotment | expected by end August 2026 |
| Build | from October 2026 |
| Commissioning | December 2027 |
| Funding | Rs550 crore debt plus internal accruals, about Rs80 crore already spent |
| Margin lift | 2 to 3 percent to 10 to 11 percent with incentives from 7 to 8 percent |
Land for the new site was offered in September 2026 .
Source: .
| Land offer Sept 2026 | Detail |
|---|---|
| Plot | Plot No. 4-3, Sector 25 at Auric Bidkin |
| Area | 127,285.98 sqm, about 31.45 acres |
| Letter | offer dated 22 Sept 2026, received 24 Sept 2026 |
The 10 lakh tonne integrated steel plant for structural steel and wire rods was kept in abeyance for water allocation of about 94.00 lakh cubic metres delayed 6 to 8 months . Investors were told to treat steel as optional for medium-term growth, with Vision 2030 built on the mill and batteries .
Mines, power and EVs: cutting cost per tonne
The board approved Rs100 crore for 50 EV dumpers for mines and steel plant . This extends a fleet that already cut haulage cost and emissions .
Sources: base fleet — ; Q1 fleet — ; solar — ; waste heat — ; melting shop — ; pellet halt and resume — .
| Step | Detail |
|---|---|
| Prior fleet | 10 EV dumpers, 24 loaders, 15 excavators, operating cost down about 75 percent, carbon dioxide down about 88 percent |
| Q1 fleet | 15 dumpers plus 24 loaders and 15 excavators |
| 25 MWp solar | commissioned 19 May 2026 at Chawardhal for Ari Dongri and Boria Tibu mines |
| 6.91 MW waste heat | started 23 June 2026 at Siltara, total waste heat to 49 MW |
| Melting shop | consent to rise from 5,25,000 to 5,75,000 tonnes per annum on 27 Oct 2026 for full captive sponge use |
| Pellet halt | 20 lakh tonne plant shut from 14 July 2026 on low monsoon ore plus costly gas and market ore, later resumed |
The captive roadmap is for Ari Dongri to rise from 23.50 lakh tonnes to 60 lakh tonnes with beneficiation and expanded pellets .
Source: .
| Roadmap | Detail |
|---|---|
| Ari Dongri | from 23.50 to 60 lakh tonnes, phased from FY27, full scale from FY28 |
| Beneficiation | capex Rs202 crore to 31 Mar 2026, commissioning by Q3 FY27 |
| Pellet | up 74 percent to 47.00 lakh tonnes in Dec 2025, 78 percent use in Q4 FY26 seen to 85 percent in FY27 |
| Reserves | 16.50 crore tonnes, 67.00 lakh tonne capacity, over 35 years life, premium Rs1,000 to Rs1,500 per tonne |
Solar is to rise from 165 MW to 540 MW for mines, pellets, mill and steel plant .
Source: .
| Solar block | Detail |
|---|---|
| Base to target | 165 MW to 540 MW |
| 25 MW | done, Rs72 crore spent to 31 Mar 2026 |
| 100 MW | in progress, Rs107 crore spent to 31 Mar 2026, due Q2 FY27 |
| 250 MW | land and line in progress, Rs89 crore spent to 31 Mar 2026 |
| 45 MWh battery | Rs31 crore spent to 31 Mar 2026, due by August |
The target was later updated to 290 MW with 150 MW on hold on mill relocation .
New EPC arm and 26 percent captive solar stake
The board backed a small in-house builder for energy projects from surplus funds .
Source: .
| GESPL term approved 13 Nov 2026 | Detail |
|---|---|
| Investment | Rs20 crore including Rs1 lakh initial via equity, loan or other mode from surplus |
| Materiality | said not material to net worth and turnover |
| Scope | turnkey work for solar, batteries, renewables, power and storage including design, supply, build, testing and maintenance |
The unit was proposed and then incorporated in Maharashtra .
Sources: proposal — ; incorporation — .
| Step | Detail |
|---|---|
| Proposal 1 Oct 2026 | Rs10 lakh for 1 lakh shares of Rs10 each, Maharashtra |
| Incorporation 17 Oct 2026 | Rs1 lakh for 10,000 shares of Rs10 each at Chhatrapati Sambhaji Nagar, fully owned in cash |
A separate captive solar stake aims to lock long-term green power for manufacturing .
Source: .
| Solarcraft term | Detail |
|---|---|
| Stake | 26 percent for Rs26 crore via equity and other securities |
| Purpose | long-term renewable power, optimise cost, raise green share |
| Project | solar in Chhattisgarh as captive plant under Electricity Act and rules |
| Materiality | said not material |
Jammu Pigments exit cleans up the books
On deciding to exit Jammu Pigments, the company booked the gap between book and fair value as a one-off and moved the rest to held for sale .
Sources: conversion — ; partial approval — ; sales — ; accounting — ; context — .
| Step | Detail |
|---|---|
| Holding after 29 June 2026 conversion | 85,69,762 shares or 43.96 percent after turning 58,92,256 preference shares, cost Rs175 crore |
| Partial sale approval 24 July 2026 | 16,75,000 shares at Rs298.45 for Rs49.99 crore to promoters, to cut to 68,94,762 shares or 35.36 percent |
| Sale 28 July 2026 | 7,74,000 shares for Rs23.10 crore, leaving 39.99 percent |
| Sale 13 Oct 2026 | 3,35,100 shares for Rs10 crore, leaving 38.27 percent |
| Sale 3 Nov 2026 | 3,67,200 shares for Rs10.95 crore, leaving 36.38 percent |
| Q2 accounting | Rs22.33 crore loss as fair minus book in exceptional items, Rs222.66 crore fair value as held for sale |
Management had said the Jammu and Kota plants were hard to run from a distance while focus stayed on Chhattisgarh and Maharashtra steel and new projects . About Rs25 crore of stock had been sold by the August 2026 call while strategy was under discussion .
What management had guided before this quarter
Q1 volume was 16 to 29 percent of full-year guidance and the company stayed on track, with value-added growth in sponge iron, billet and rolled output . Margin recovery was guided from Q4 FY27 after beneficiation lifts captive pellet use .
Source: .
| Product | FY26 performance | FY27 target |
|---|---|---|
| Iron ore mining (million tonnes) | 2.75 against 3.0 at 92 percent | 3.4 |
| Pellets (million tonnes) | 2.86 against 3.0 at 95 percent | 4.0 |
| Sponge iron (million tonnes) | 0.65 against 0.594 at 109 percent | 0.65 |
| Billets (million tonnes) | 0.48 against 0.5 at 96 percent | 0.525 |
| Rolled (million tonnes) | 0.421 against 0.375 at 112 percent | 0.44 |
| Ferro alloys (tonnes) | 94,423 against 91,500 at 103 percent | 95,000 |
Steel demand was seen strong on infrastructure, housing, railways and manufacturing .
Source: .
| Demand view Aug 2026 | Detail |
|---|---|
| India steel demand | strong on infrastructure, housing, railways and manufacturing |
| India iron ore output FY27 | up 8 percent to 34 to 34.50 crore tonnes, mostly captive mines |
| Pellet output | 12 crore tonnes in FY26 against 10.90 crore tonnes in FY25 |
| Utilisation | constrained at 65 percent on lower exports and high-grade shortage |
| Global ore | 95 to 105 dollars per tonne |
| Domestic ore | around Rs5,500 ex-mine |
The May call saw FY27 top line over Rs6,000 crore with EBITDA of 24 to 25 percent at current market levels . The board also changed stock option vesting terms subject to shareholders, adopted a biodiversity policy and revised conduct code, and adopted a new brand with no change in legal name, shareholding or operations . The new identity was framed as One Godawari Powering New Horizons across mining, steel, ferro alloys and power with storage, healthcare and real estate .
---
Sources
- 1 Submission of Results for the period ended 30.09.2026.
- 2 Godawari Power and Ispat Ltd — historical financial matrix and financial statement analysis
- 3 Investor presentation, 2026-05-19
- 4 Earnings-call transcript, 2026-08-13
- 5 Earnings-call transcript, May 2026
- 6 Godawari Power and Ispat Ltd - 532734 - Announcement under Regulation 30 (LODR)-Acquisition
- 7 Announcement under Regulation 30 (LODR)-Acquisition
- 8 Godawari Power and Ispat Ltd - 532734 - Announcement under Regulation 30 (LODR)-Acquisition
- 9 Godawari Power and Ispat Ltd - 532734 - Announcement under Regulation 30 (LODR)-Acquisition
- 10 [Godawari Power and Ispat Ltd - 532734 - Environment Clearance Received By The Godawari New Energy Private Limited (A Wholly Owned Subsidiary Company) For Construction Of Industrial Building At
- 11 Godawari Power and Ispat Ltd - 532734 - Intimation Regarding Receipt Of Offer Letter For Allotment Of Industrial Land At AURIC Bidkin Industrial Area, Maharashtra.
- 12 Godawari Power and Ispat Ltd - 532734 - Commencement Of Operations At 25 Mwp Captive Solar Power Plant.
- 13 Commencement Of Commercial Operations At 6.91 MW Waste Heat Recovery Based Power Plant Situated At Siltara Industrial Area, Raipur, Chhattisgarh.
- 14 Godawari Power and Ispat Ltd - 532734 - Receipt Of "Consent To Operate" The Enhanced Capacity Of Steel Melting Shop (SMS) From 5,25,000 MTPA To 5,75,000 MTPA.
- 15 Godawari Power and Ispat Ltd - 532734 - Temporarily Suspension Of Operations At 2.00 MTPA Iron Ore Pellet Plant Situated At Phase - II, Siltara Industrial Area, Raipur, Chhattisgarh W.E.F. 14.07.2026.
- 16 Godawari Power and Ispat Ltd - 532734 - Intimation About Resumption Of Operations In 2.00 MTPA Iron Ore Pellet Plant Situated At Phase-II, Siltara Industrial Area, Raipur, Chhattisgarh.
- 17 Godawari Power and Ispat Ltd - 532734 - Announcement under Regulation 30 (LODR)-Acquisition
- 18 Godawari Power and Ispat Ltd - 532734 - Announcement under Regulation 30 (LODR)-Acquisition
- 19 Godawari Power and Ispat Ltd - 532734 - Announcement under Regulation 30 (LODR)-Acquisition
- 20 Godawari Power and Ispat Ltd - 532734 - Approval For Partial Divestment Of Investment In Jammu Pigments Limited.
- 21 Godawari Power and Ispat Ltd - 532734 - Updates On Disposal Of Stake In Jammu Pigments Limited, An Associate Company
- 22 Godawari Power and Ispat Ltd - 532734 - Updates On Disposal Of Stake In Jammu Pigments Limited, An Associate Company.
- 23 Godawari Power and Ispat Ltd - 532734 - Updates On Disposal Of Stake In Jammu Pigments Limited, An Associate Company.
- 24 Announcement under Regulation 30 (LODR)-Press Release / Media Release